Construction Update: Week Ending July 31, 2020

As July draws to a close, we’re happy to share more of the progress made by our contracting crews at the construction site of the Research and Innovation Center. Here’s what was completed this week:

  • Overhead FMEP on levels 1 through 5
  • Mechanical and plumbing insulation
  • Lights on levels 1 through 3
  • Miscellaneous framing and drywall on levels 1 through 5
  • Ceiling grid installation on levels 1 through 3
  • Paint on levels 1 through 5
  • Tile for the level 1 floor
  • Flooring on levels 1 through 3
  • DIRTT walls on levels 1 through 3
  • Seat walls and patio
  • Irrigation and landscaping
  • North grading and paving

As always, check back with us soon for more news!

Read More

Construction Update: Week Ending July 24, 2020

As we near the start of August, progress hasn’t stopped at the construction site of the Research and Innovation Center! Here’s what the crews completed this week:

  • Overhead FMEP on levels 1 through 5
  • Mechanical and plumbing insulation
  • Lights on levels 1 through 3
  • Plumbing fixtures
  • Miscellaneous framing and drywall on levels 1 through 5
  • Ceiling grid installation on levels 1 through 3
  • Paint on levels 1 through 5
  • North brick and precast
  • Tile on level 1 floor and walls
  • Flooring on levels 1 through 3
  • Seat walls and patio
  • Irrigation and landscaping
  • North grading and paving
  • DIRTT walls on levels 1 and 2

Keep checking back with us for more updates!

Read More

Construction Update: Week Ending July 10, 2020

We’re happy to share more interior and exterior progress at the construction site of the Research and Innovation Center. Here’s what our crews completed this week:

  • Overhead FMEP on levels 1 through 5
  • Mechanical and plumbing insulation
  • Lights on levels 1 through 3
  • Plumbing fixture installation
  • Drywall on levels 1 through 5
  • Ceiling grid installation on levels 1 through 3
  • Paint on levels 1 through 5
  • North brick and precast
  • Tile on the level 2 floor and walls
  • Flooring on level 3
  • Seat walls and patio
  • Irrigation and landscaping
  • DIRTT walls on level 1

See the latest photos above.

Read More

Construction Update: Week Ending July 3, 2020

As Independence Day quickly approaches, we’re back with another update! Here’s what our teams at the construction site of the Research and Innovation Center completed this week:

  • Overhead FMEP on levels 1 through 5
  • Mechanical and plumbing insulation
  • Lights on levels 1 through 3
  • Installation of plumbing fixtures
  • Drywall on levels 1 through 5
  • Ceiling grid on levels 1 through 3
  • Paint on levels 1 through 5
  • Storefront at Buckhoist
  • North brick and precast
  • Tile on the floor and walls of level 3
  • Seat walls and patio
  • Irrigation
  • Window sills and stool trim
  • DIRTT walls on level 1

View this week’s photos above, and be sure to check back soon for more updates.

Read More

Construction Update: Week Ending June 26, 2020

Welcome back to another update on the progress at the Research and Innovation Center construction site! Here’s what our contracting teams completed this week:

  • Overhead FMEP on levels 1 through 5
  • Mechanical and plumbing insulation
  • Lights on levels 1 through 3
  • Plumbing fixtures
  • Drywall on levels 1 through 5
  • Ceiling grid on levels 1 through 3
  • Paint on levels 1 through 5
  • Storefront at Buckhoist
  • North brick and precast
  • Tile of level 4 floor and walls
  • Flooring on level 2
  • Seat walls and patio
  • Irrigation
  • DIRTT walls on level 1

See this week’s photos above, and check back with us again soon for another update.

Read More

Construction Update: Week Ending June 5, 2020

We’re back with another update on the progress at the Research and Innovation Center construction site! Here’s what the team completed this week:

  • Overhead FMEP on levels 1 through 5
  • Mechanical and plumbing insulation
  • Drywall on levels 1 through 5
  • Ceiling grid on level 1
  • Paint on levels 1 through 3
  • Curtainwall trimout
  • North brick and precast
  • Elevators
  • Tile in the kitchen, of the level 1 floor, and in the level 4 bathroom
  • Sitework – MRI Drive tie-in
  • Dumpster canopy

We’ll be back soon with more updates – see this week’s photos above.

Read More

Construction Update: Week Ending May 22, 2020

We’re pleased to share another week of progress at the construction site of the Research and Innovation Center. Here’s what was accomplished this week:

  • Overhead FMEP on levels 1 through 5
  • Mechanical and plumbing installation
  • Drywall on levels 2 through 5
  • Ceiling grid on level 2
  • Paint on level 3
  • North elevation curtainwall and storefront
  • East brick and precast
  • Northeast precast
  • Elevators
  • Tile in the kitchen, and bathrooms on levels 2 through 4

Check out this week’s photos above.

Read More

Construction Update: Week Ending May 8, 2020

Progress continues at the construction site of the Research and Innovation Center. Here’s what our contractor teams completed this week:

  • Overhead FMEP on levels 1 through 5
  • In-wall mechanical, electrical, and plumbing on level 5
  • Mechanical and plumbing insulation
  • Interior framing on level 5
  • Drywall on levels 2 and 3
  • Paint on levels 1 and 2
  • North elevation curtainwall and storefront
  • South brick and precast
  • East brick and precast
  • Elevators
  • Tile in the kitchen, and in the level 1 and level 2 bathrooms

See this week’s photos above and be sure to check back next week for more updates!

Read More

Construction Update: Week Ending May 1, 2020

Another week of work is complete at the construction site of the Research and Innovation Center. Here’s what was accomplished by our hard-working contracting crews:

  • Overhead FMEP on levels 1 through 5
  • In-wall mechanical, electrical, and plumbing on level 5
  • Mechanical and plumbing insulation
  • Interior framing on level 5
  • Soffit framing on level 4
  • Drywall on levels 2 through 4
  • North elevation curtainwall and storefront
  • South brick and precast
  • East brick and precast
  • Metal roofing
  • Elevators
  • Tile in kitchen and level 1 bathrooms

Check out this week’s photos above.

Read More

Construction Update: Week Ending April 17, 2020

Welcome back! We’ve got another update for you on the progress at the Research and Innovation Center construction site. Here’s what was wrapped up during this week:

  • Overhead FMEP on levels 1 through 5
  • In-wall mechanical, electrical, and plumbing on levels 2 through 5
  • Mechanical/plumbing insulation
  • Interior framing on level 5
  • Soffit framing on level 3 and 4
  • Drywall on level 1
  • East elevation curtainwall and storefront
  • North elevation curtainwall and storefront
  • South brick and precast
  • Metal roofing
  • Elevators