Construction Update: Week Ending July 3, 2020

As Independence Day quickly approaches, we’re back with another update! Here’s what our teams at the construction site of the Research and Innovation Center completed this week:

  • Overhead FMEP on levels 1 through 5
  • Mechanical and plumbing insulation
  • Lights on levels 1 through 3
  • Installation of plumbing fixtures
  • Drywall on levels 1 through 5
  • Ceiling grid on levels 1 through 3
  • Paint on levels 1 through 5
  • Storefront at Buckhoist
  • North brick and precast
  • Tile on the floor and walls of level 3
  • Seat walls and patio
  • Irrigation
  • Window sills and stool trim
  • DIRTT walls on level 1

View this week’s photos above, and be sure to check back soon for more updates.