- North Canopy
- Northeast Elevation
- Seatwall Brick
- Bioswell Soil Mixing
- Generator Installation
- Level 1 Wall Tile
We’re happy to share more interior and exterior progress at the construction site of the Research and Innovation Center. Here’s what our crews completed this week:
- Overhead FMEP on levels 1 through 5
- Mechanical and plumbing insulation
- Lights on levels 1 through 3
- Plumbing fixture installation
- Drywall on levels 1 through 5
- Ceiling grid installation on levels 1 through 3
- Paint on levels 1 through 5
- North brick and precast
- Tile on the level 2 floor and walls
- Flooring on level 3
- Seat walls and patio
- Irrigation and landscaping
- DIRTT walls on level 1
See the latest photos above.