Construction Update: Week Ending May 22, 2020

We’re pleased to share another week of progress at the construction site of the Research and Innovation Center. Here’s what was accomplished this week:

  • Overhead FMEP on levels 1 through 5
  • Mechanical and plumbing installation
  • Drywall on levels 2 through 5
  • Ceiling grid on level 2
  • Paint on level 3
  • North elevation curtainwall and storefront
  • East brick and precast
  • Northeast precast
  • Elevators
  • Tile in the kitchen, and bathrooms on levels 2 through 4

Check out this week’s photos above.