Construction Update: Week Ending May 1, 2020

Another week of work is complete at the construction site of the Research and Innovation Center. Here’s what was accomplished by our hard-working contracting crews:

  • Overhead FMEP on levels 1 through 5
  • In-wall mechanical, electrical, and plumbing on level 5
  • Mechanical and plumbing insulation
  • Interior framing on level 5
  • Soffit framing on level 4
  • Drywall on levels 2 through 4
  • North elevation curtainwall and storefront
  • South brick and precast
  • East brick and precast
  • Metal roofing
  • Elevators
  • Tile in kitchen and level 1 bathrooms

Check out this week’s photos above.