Construction Update: Week Ending March 6, 2020

As the clouds and rain have cleared up toward the end of this week, we’re happy to share some new photos of the progress of the Research and Innovation Center’s construction, along with the recap. Here’s what our construction teams completed this week:

  • Overhead mechanical, electrical, and plumbing on levels 1 through 5
  • In-wall mechanical, electrical and plumbing on levels 1 through 4
  • Interior framing on levels 4 and 5
  • Exterior framing on levels 3 through 5
  • Southwest elevation curtainwall & storefront
  • West level 1 precast and brick
  • Roof blocking

We’ll be back next week with more!