Construction Update: Week Ending February 7, 2020

It’s been another busy week at the Research and Innovation Center construction site, and the building is really taking shape. Here’s what our contractors were hard at work on this week:

  • Overhead mechanical, electrical, and plumbing on levels 1-4
  • Interior framing for level 3 and level 4
  • Exterior framing on levels 3-5
  • Miscellaneous roof steel detail
  • Fireproofing on level 4
  • In-wall mechanical, electrical, and plumbing on levels 1-3
  • South elevation waterproofing
  • West elevation curtainwall and storefront
  • Penthouse slab pour

We’ll be back next week with more updates. See this week’s photos above!