Construction Update: Week Ending January 17, 2020

Happy Friday! We’re back with another update from the Research and Innovation Center construction site. Here’s what was completed this week:

  • Overhead mechanical, electrical, and plumbing on levels 1, 2, and 3
  • Interior framing on level 1 and level 2
  • Exterior framing on levels 1, 2, 3 and 4
  • Miscellaneous steel erection and welding
  • Drywall topout on level 1
  • Elevated slab pouring
  • Fireproofing on level 4
  • In-wall electrical on level 1

We’ll see you next week with more! Browse this week’s photos above.