We’re back! Despite the weather leaving the Plains cold and wet this week, the hard-working team of contractors at the Research & Innovation Center construction site have continued to make valuable progress, keeping us on-track. Here’s what they completed this week:

  • Steel erection sequence 4 and 5
  • Placement of overhead mechanical, electrical, and plumbing elements on levels 1 and 2
  • Roughing-in of the storage building
  • Work on the block walls at the storage building
  • Miscellaneous steel welding
  • Dumpster drain tie-in